ISLAMABAD: While adopting a strategic fast-track strategy, the Oil & Gas Development Company Limited (OGDCL) has successfully completed the Khewari (Suleman 1 & 2) Development Project.
The Khewari Development Project has potential of 10 million standard cubic feet per day (MMSCFD) which is being processed at the Sinjhoro Plant in the Sanghar district of Sindh province.
Currently, the wells are undergoing choke optimization process to further enhance gas supply.
To expedite the project, OGDCL implemented a fast-track strategy, ensuring swift processes and timely delivery. This included laying a 6-inch diameter pipeline covering a distance of 14.5 kilometers from the Gathering Facility near Suleman-1 to the Chabaro Tie-in point, facilitating early first gas injection into the SSGC system.
The Khewari Development Project is a joint venture with OGDCL serving as the operator and holding a 77.50% stake.
GHPL holds 22.50% share. This achievement is part of OGDCL’s broader initiative to enhance efficiency, optimize production, and contribute in mitigating energy demand through indigenous resources. OGDCL is committed to ensuring a sustainable and reliable energy future for the nation.
JERUSALEM (Reuters): Israeli war cabinet minister Benny Gantz demanded on Saturday that Prime Minister Benjamin…
HANOI: Vietnam’s governing Communist Party has nominated the public security minister to be the next…
TORONTO (Reuters): Some Canadian provinces have logged a jump in unclaimed dead bodies in recent…
SAN FRANCISCO (AFP): A man who attacked the elderly husband of former US House Speaker…
F.P. Report ISLAMABAD: Prime Minister Shehbaz Sharif on Saturday decided to send Deputy Prime Minister…
F.P. Report LAHORE: Pakistan Muslim League-Nawaz supremo Mian Nawaz Sharif reiterated his long held position…
This website uses cookies.